Belagavi Bypass Construction Tenders Invited
Belagavi Bypass: Request for Proposal (RFP) for Construction of a 4-6 Lane Bypass for the City of Belagavi from Km 11.00 (Goa side) of NH-4A to Km 516.000 (Pune side) of NH-4 (Design Length 34.480 km) in the State of Karnataka on Hybrid Annuity Mode 1A package.
The development, upkeep, and management of National Highway No. NH-48 and (former NH-4A), including the portion from Km 11.00 (Goa side) of NH-4A to Km 516.000 (Pune side), has been given to the Authority by the Government of India (approx. 34.480 km).
Table of Contents

The Authority had resolved to augment the existing road from Km 11.00 (Goa side)) of NH-4A to Km 516.000 (Pune side) of NH-4 (Design Length 34.480 km) on the Belagavi Bypass city section of National Highway No. NH-48 and (old NH-4A) (hereinafter called the “NH-48 and (old NH-4A) 4/6 Lane bypass for Belagavi city”)
Tender Details:
The National Highway No. NH-48 and (old NH-4A) 4/6 Lane Bypass for Belagavi City” Project) on design, build, operate, and transfer (the “DBOT Annuity” or “Hybrid Annuity”) basis in the State of Karnataka. The existing road from Km 11.00 (Goa side) of NH-4A to Km 516.000 (Pune side) of NH-4 (Design Length 34.480 km) would The following are the project’s brief details:
Name of the Highway | Length (in Km) | Estimated Project Cost (Excluding GST) (In Rs. Cr.) |
Construction of 4/6 Lane bypass for Belagavi city from Km 11.00 (Goa side) of NH-4A to Km 516.000 (Pune side) of NH-4 (Design Length 34.480 km) in the state of Karnataka on Hybrid Annuity Mode. Package 1A. | 34.480 | 1167.10 |
Tender/Bid Submission Site:
Bids must be submitted online only at http://etenders.gov.in during the period of registration with the NHAI e-Tendering Portal being managed by the National Informatic Centre (NIC), i.e. http://etenders.gov.in on or before 21.02.2023. The complete BID document can be viewed/downloaded from the e-procurement portal of NHAI at http://etenders.gov.in from 02.01.2023 to (upto 1100 hours IST). On February 22, 2023, technical submissions for the online-submitted bids will be made available (at 1130 hours IST).
Note: Any other method of submitting a bid will not be accepted. However, before the Authority issues the Letter of Award (LOA), the Lowest Bidder must physically submit the original copies of all the documents required by clause 2.11.2 of the RFP, including the Bid Security, Power of Attorney for signing the Bid, Power of Attorney for the lead member of the Consortium, if any, Joint Bidding Agreement for Consortium, if any, Integrity Pact, and experience certificates apostille at the foreign origin if any.
PACKAGE DETAILS CONSTRUCTION OF BELAGAVI BYPASS:
(Package-1A)
Stretch: Construction of 4/6 lane Belagavi Bypass from Km 11.00 (Goa side) of NH-4A to Km 516.000 (Pune side) of NH-4 (Design Length 34.48 km) in the State of Karnataka on Hybrid Annuity Mode. (Package 1A)
Length: 34.480 Km
Start point: Ch. 11.00 Km (Goa side) of NH-4A near Zadshahapur Village
End point: Ch. 516.00 Km (Pune side) of NH-4 near Bennalli Village
Lane configuration: 4/6 lane divided carriageway with service road
Proposed row: 60M
Speed: 100 Kmph
Type of pavement: Rigid Pavement
Land to be acquired: 260 Ha
Cost of land: ₹73 crores
Cost of land to be acquired : *(State Government of Karnataka has allotted 140 Crs towards 50% of the total LA cost of the project of length 69.427km)
Total capital cost: ₹1094 Cr
Per km total capital cost: ₹31.70 cr/km